Prepare for the Florida General Contractor Exam. Study with flashcards and multiple choice questions, each question includes hints and explanations. Get exam-ready now!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


According to AIA 201, which of the following will NOT be considered by the architect when calculating the cost of a change directive?

  1. Time of completion

  2. Impact on project schedule

  3. Market conditions

  4. Quality of materials

The correct answer is: Market conditions

The architect's consideration when calculating the cost of a change directive revolves primarily around factors that directly impact the project scope, schedule, and overall execution. In this context, the correct choice highlights an aspect that is typically external and less controlled by the architect's immediate influence. When assessing a change directive, the time of completion and the impact on the project schedule are essential elements, as they directly relate to how the alteration will affect project timelines and deadlines. The quality of materials is also a critical factor because changes might necessitate different materials, which can lead to variations in cost depending on the type and quality required for the project. Conversely, market conditions refer to the broader economic environment, including pricing changes, availability of materials, labor costs, and other market dynamics. While these conditions certainly affect overall construction costs, they are not parameters that architects directly consider when calculating the specific costs associated with a change directive. Thus, market conditions are often seen as external influences that may not be reflected in the immediate factors of the project’s scope or execution.